CONSTRUCTION TIMELINE
Schedule for Completion of Intermediate and Primary Schools
NCCS CONSTRUCTING TWO NEW SCHOOLS
Background
Thanks to the support of the residents of North Canton City Schools, the district is constructing two new school buildings that will replace five building currently in use. A new Pre-K through grade two building will house students that presently attend the Early Childhood Center, Clearmount Elementary, and Northwood Elementary. The site of the new primary school is located on Charlotte Street. A new intermediate school, housing grades three-five, will be located on the present Clearmount site and will face East Maple Street. This school replaces Greentown Intermediate and Orchard Hill Intermediate Schools.
LOGISTICS PLAN FOR CHARLOTTE BUILDING SITE
New Primary School
This site map shows the Charlotte location for the new school building that will house grades preschool through second grade. Note the location of new school in relation to the present Mary L. Evans Early Childhood Center.
LOGISTICS PLAN FOR CLEARMOUNT BUILDING SITE
New Intermediate School
This site map shows the Clearmount location for the new school building that will house grades 3-5. Note the construction area where the new building will be erected. The map also shows where a drop-off and pick-up area for current Clearmount Elementary students.
The new intermediate school will be located at the Clearmount site. These photos show the exterior of the planned building.
DESIGN AND DEVELOPMENT OF NORTH CANTON PRIMARY AND INTERMEDIATE SCHOOLS
North Canton Primary School Concept Plans
North Canton Intermediate School Concept Plans
SCHEMATIC DESIGN OF NCCS PRIMARY AND INTERMEDIATE SCHOOL BUILDINGS
FACILITY PLANNING UNDERWAY
Thanks to the support of the North Canton City School District residents, work has begun on the facility project that will result in two new school buildings in the district. The Mary L. Evans Early Childhood Center, Clearmount Elementary School, and Northwood Elementary will be consolidated into one building. Greentown Intermediate and Orchard Hill Intermediate will be combined into another new school.
A steering committee, which meets every two weeks, has been created to make recommendations about the construction of each school building, such as classroom components, lockers, cafeteria size, number of restrooms, and sizes of extended learning areas.
Timeline for construction:
Late summer/fall 2021: Excavation work
Nov./Dec. 2021/January 2022: Bidding process for building components - foundation/plumbing/HVAC/electricity/etc.
February 2022: Construction begins weather permitting
August 2023: School buildings open
Steering Committee:
NCCS District Personnel
Superintendent Jeff Wendorf
Asst. Superintendent Dave Pilati
Treasurer Todd Tolson
Business Manager Todd Henne
Technology Director Kim Nidy
Board of Education
Jessica Stroia
Robert Roden
City Administrator for City of North Canton Pat DeOrio
Hammond Construction
John Kirkpatrick, Jeff Adams, Frank Mongiardo
SoL Harris/Day
Domenic Ferrante, Burt Marzley, Jordan Lewis Regina Erdman, and Carolina Silva
Parents
Holly Pierpont, Larry Kinard, and Andy Schiltz
NCCS Staff
Alyssa Wise
Amanda Chaney
Candice Robinson
Darlene Howald
David Russ
Denise Cooley
Janet Peare
Jarrod Thomas
Jennelle Ellis
John Welch
Josh Runner
Kerrie Steepleton
Kristi Cropper
Matthew Donaldson
Melissa Wolfe
Ryan Kumpf
Terri Simmons
Tiffany Humphrey
*Article from the November 2020 Viking Vision
BACKGROUND INFORMATION ON PROJECT
Student Enrollment
2019 Enrollment Report
Master Planning Process
Informational Placemat
Site Studies
Conceptual Site Studies - PK-2
Conceptual Site Studies - 3-5
CONSTRUCTION DATES OF SCHOOL BUILDINGS AND FACILITIES
RESOURCES
SEVENTH STREET RENOVATION FOR APRIL 28, 2023
PRIMARY SCHOOL UPDATE FOR APRIL 21. 2023
NC INTERMEDIATE SCHOOL FOR APRIL 6, 2023
NORTH CANTON PRIMARY SCHOOL FOR MARCH 31
MEMORIAL STADIUM MARCH 17, 2023
INTERMEDIATE SCHOOL CONSTRUCTION MINUTE FOR MARCH 3, 2023
STADIUM GRANDSTAND AND BUS GARAGE FOR FEBRUARY 10
NC PRIMARY SCHOOL UPDATE FOR FEBRUARY 3
INTERMEDIATE SCHOOL UPDATE FOR JANUARY 20
CONSTRUCTION MINUTE FOR JANUARY 20TH
CONSTRUCTION MINUTE FOR DECEMBER 9TH
CONSTRUCTION MINUTE FOR NC PRIMARY DECEMBER 2
DEMOLITION OF GRANDSTAND AT NC MEMORIAL STADIUM NOVEMBER 11, 2022
INTERMEDIATE SCHOOL CONSTRUCTION UPDATE FOR NOVEMBER 4
PRIMARY SCHOOL FOR OCTOBER 28
NORTH CANTON INTERMEDIATE SCHOOL UPDATE FOR OCTOBER 21
CONSTRUCTION MINUTE ON NORTH CANTON PRIMARY SCHOOL FOR OCTOBER 14
BEAM SIGNING BY PRE-K TO GRADE 5 STUDENTS AND STAFF OCTOBER 7
INTERMEDIATE CONSTRUCTION MINUTE SEPTEMBER 30
PRIMARY CONSTRUCTION MINUTE FOR SEPTEMBER 23
INTERMEDIATE CONSTRUCTION MINUTE FOR SEPTEMBER 16
PRIMARY SCHOOL CONSTRUCTION MINUTE FOR SEPTEMBER 9
The primary building continues to make steady progress. The slab on grade is almost finished, including the gym floor, while the steel and masonry work continues. Second floor joist and deck materials continue to arrive on schedule along with each sequence of steel. We anticipate roof decking to be delivered early in September and the second-floor sabs will continue to be poured in sequence. Finally, the west side of the site is moving forward as curbs have been poured, and a significant part of the west parking lot and driveway will be asphalted in the next two weeks.
The intermediate building continues to move forward in a similar fashion with the slab on grade almost completely finished. A significant number of interior block walls have been constructed, and steel and joist continue to be installed each day. Today marked the first pour of the second-floor slab in the area nearest Clearmount, and those pours will continue through the next couple of weeks. We anticipate exterior framing of this building will begin shortly after Labor Day. Some preliminary site work has already been completed along the east side of the building, which will be part of the future bus parking area.